First Solar cuts 2026 guidance as tariff uncertainty slows module orders

Third-quarter net sales fell 23% year over year to $1.23 billion, while margins and profit improved and the company shifted toward project-specific contracts.

First Solar has lowered its full-year 2026 volume and revenue guidance after third-quarter module orders slowed, with executives pointing to unresolved trade policy questions following the August Section 232 tariff proclamation.

The company reported $1.23 billion in net sales for the third quarter of 2026, a 58% gross margin and $571 million in net income. Net sales fell 23% year over year on lower volumes of modules sold to third parties, but gross margin came in roughly 20 percentage points above the prior-year quarter and net income rose 25%. First Solar also authorized a new $500 million share buyback.

Full-year volume sold is now expected at 16.0 GW to 17.0 GW, and net sales guidance was cut to $4.6 billion to $4.9 billion, down from the $4.9 billion to $5.2 billion range issued after the second quarter.

Contracting moves to individual projects

First Solar closed the quarter with a contracted backlog of 44 GW valued at about $13.5 billion, with deliveries scheduled through 2030. Since its second-quarter update, the company recorded 1.4 GW of U.S. bookings at an average selling price of roughly 36 cents per watt.

CFO Alex Bradley said the company does not intend to place international volume on the spot market, calling it a challenging place to be, and is instead shifting toward project-specific contracts with defined delivery schedules rather than the multi-year framework agreements with very large customers that First Solar has traditionally used. Bradley said the approach supports more efficient operational planning and reduces working capital requirements and warehousing costs, even though it slows the rate at which multi-year backlog accumulates.

Section 232 and the Malaysia decision

CEO Mark Widmar described the August proclamation as a structural change in how the United States approaches solar manufacturing, noting that nearly 80% of First Solar's global manufacturing footprint will sit in the United States by 2027. He said the company, as the only fully integrated utility-scale solar manufacturer without dependence on a Chinese crystalline silicon supply chain, is structurally positioned to benefit from that environment.

Near-term procurement has nonetheless slowed. Widmar said developers are holding back module purchases for 2029 and 2030 as they work through interconnection constraints and local pushback on data center deployment, await further guidance on Foreign Entity of Concern rules, and weigh how Section 232 minimum import prices and anti-stockpiling provisions will be enforced.

The pressure falls hardest on Southeast Asian Series 6 output. The Vietnam plant is slated to supply semi-finished Series 6 modules to First Solar's newly inaugurated South Carolina finishing facility, while the 1.8 GW Malaysia factory continues to produce finished international modules. Widmar said a binary decision on Malaysia will come in the first half of 2027: run the plant at full or near-full capacity, or halt production altogether. Because Malaysian modules do not qualify for Section 45X manufacturing tax credits and carry freight and tariff costs, the company does not expect either outcome to materially affect its run-rate earnings profile.

Perovskite licensing and warranty litigation

Shortly before the earnings call, First Solar announced a non-exclusive patent licensing agreement with perovskite company CubicPV, adding those rights to its existing agreement with Oxford PV. The company plans to begin producing Series 6-form-factor perovskite modules at its Perrysburg, Ohio facility in the first half of 2027 for field testing and durability validation.

On legal matters, Widmar said First Solar will soon file its formal response in a warranty lawsuit brought by developer Swift Current Energy, and maintained that the company's warranty terms govern any remediation. He said First Solar would stand by and support the obligations it has under the parameters of its limited liability warranty, and that remedies sought outside those parameters are not something the company will provide. Separately, disputes over the company's TOPCon intellectual property remain ongoing.

NP

Nadia Petrova

Nadia Petrova is an editorial analyst covering nickel-based alloys, titanium bar and plate, and refractory metals for industrial engineering and manufacturing. Her coverage compares reported chemical composition, room temperature tensile results under ISO 6892-1, and immersion corrosion data under stated media and temperature, while distinguishing test specimens from finished service conditions. She helps materials engineers, metallurgists, and sourcing leads evaluate temperature limits, corrosion environments, and supplier evidence for a defined application without treating any alloy as universally suitable.